Issue details
Vulcan Works Creative Hub Fit Out and Additional Roof Works
To update Cabinet on the progress being made on the construction of the Vulcan Works Creative Hub and to seek approval for the drawdown of ringfenced funds for the fit out of the centre and towards the cost of the roof works.
The report will also seek update cabinet on the procurement process for the operator of the facility and seek delegated authority for the appointment of the successful contractor following an OJEU compliant procurement process.
Decision type: Key
Decision status: For Determination
Notice of proposed decision first published: 23/02/2021
Reason Key: Financial;
Decision due: 24 Mar 2021 by Cabinet
Lead member: Cabinet Member for Regeneration and Enterprise
Lead director: Kevin Langley
Department: Regeneration, Enterprise & Planning
Contact: Kevin Langley, Economic Growth and Regeneration Manager Email: KLangley@northampton.gov.uk Email: KLangley@northampton.gov.uk.
Public or Private: Public